This week, work continues on the west side of Level 4 with call numbers P (literature and language) and Q (science). …Continue Reading Mullins Renovation: Week of July 16
Mullins Renovation: Week of July 16
This week, work continues on the west side of Level 4 with call numbers P (literature and language) and Q (science). …Continue Reading Mullins Renovation: Week of July 16
Movers are now working on Level 4, in the call number ranges T-Z and R-S, with a few Qs, as well. Audio and video materials are also affected. …Continue Reading Mullins Renovation: Week of July 9
Moving Continues on Level 3: Call numbers A – HF and Oversized areas are affected. …Continue Reading Mullins Renovation: Week of June 25
Call numbers affected this week are LRC and west side E 1 – HF 9999. …Continue Reading Mullins Renovation: Week of June 18
This week, the move of materials to the new facility begins, starting with call number areas HG – HX on Level 3 and M – N on Level 1. View the floor maps for details of the affected areas. …Continue Reading Mullins Renovation: Week of June 11
They’re here! The movers will be bringing their equipment to Mullins Library this Sunday, June 10. They will begin moving starting on levels 1 and 3. …Continue Reading Mullins Renovation: Week of June 4